East India Petroleum (P) Limited is the first company in the Private Sector, to set up a port-based world-class facility for receipt, storage and handling of POL Products, Petro-Chemicals and LPG. The Terminal is constructed on 50 acres of land located at Visakhapatnam Port , on the east coast of India .

 







 
 

Designed and constructed as per following codes/standards

•  Oil Industry Safety Directorate ( OISD) 117 & 118

•  Chief Controller of Explosives (CCOE) Regulations

•  Static and Mobile Pressure Vessels (SMPV) Rules

•  Petroleum Rules

•  Tariff Advisory Committee (TAC) Norms

•  Regulations of Electrical Inspectorate

•  Regulations of Inspector of Factories

•  Andhra Pradesh Pollution Control Board

•  American National Standards Institute (ANSI)

•  American Society for Testing and Materials ( ASTM)

•  (British Standards) BS & (International standards)

•  IS for design, fabrication, materials and inspection

 

EIPPL is one of the four companies short-listed by IOC for their projects on Build and Operate basis. It is one of the few companies in the private sector having vast operational experience as well as the capability to design, construct and commission top-tier storage terminals.
The 10-year operations experience coupled with the 7-year ISO/OHSAS experience has further enhanced EIPPL's design capability.

Terminal specific software covering all terminal areas/operations including inventory and HR functions.

Spacious layout of the terminal over an extensive 50-acre plot.

Multiple Tank Design including floating roof, fixed roof and fixed with internal floating roof.

All tanks are 100% Class A Construction ( MS construction).

Terminal connected to both the liquid cargo jetties in the inner harbor and is serviced by three dedicated piggable pipelines, two of 14" diameter and one of 12" diameter. Each of the three pipelines is 5.2 KM in length.

Nitrogen from EIPPL's nitrogen plant located at the jetty is used for pigging operations to ensure pipeline and product integrity.
For LPG the terminal is connected to the outer harbor jetty through a 7.1 km long, 10" diameter pipeline.
100% power backup through Diesel Generators.
Handling systems designed to minimize losses to negligible levels.
6 tanker trucks loading bays with permission for adding two more bays to the existing gantry; and another 8 bay gantry.
Loading bays are equipped with individual supply lines, loading arms and automatic flow meters.
Two 50 MT capacity electronic weighbridges.
Fully equipped Emergency Control Room and Operations. Control Room manned 24 hrs x 365 days.
Project co-ordination, construction, quality control and commissioning were done in-house by EIPPL personnel.
   
 